Results of Project

Date Tasks Responsible person Status
19.5. – 5.7. developing main product (draw the recipes, exact- EE done
ly written procedures for the preparation of a unit
6.7. – 27.7. set of dishes) EE done 3. 7. 99
28.7. – 17.8. looking for solutions to the elimination of bottle-
necks (transport to the customer, time of transport, Student done + PG
delivery to a different address) Student done + OgH
refine the recipe for bread products Students not searching
Student
formulation of energy and nutrition Student done
done
looking for partnership on ingredients; suppliers EE working mentor

perform tastings; market feedback INF logo done
INF in the implementation
accurately identify operating procedures Students
INF gave up
review the good work practices from abroad in the gave up
transport of food to the final customer INF
in Photoshop to prepare a graphic design shop CE gave up
INF done
draw the graphic image of bags CE done (web site)
EE gave up
examine the best way to pack dishes: (legislation) internet
Student
solutions for system procurement / bottlenecks in gave up
receipt of orders (GPS)
Plan B: the collapse of websites: quality is free

preparation of the promotional material

what is the possibility of a virtual application

what is our opportunity to advertise

define the advertising costs, the result of: (a good
voice reaches you in the ninth)
help center for purchaser (on-line or phone)

18.8. – 30.9. analyzing the sales funnel / conversion on your site INF gave up
expanding offer according to the customer CE 3. theme item
sales week at VŠUPNM Student done, october
preparation of reports CE
production of brochure + A1 CE done
done

Comments: EE – team of economists, CE – the whole team, INF – informatics.
Source: Own source 2014; Crosby 1979; Slaughter, Archerd, and Campbell 2004.

The main websites for the project are http://pkpsandwich.weebly.com/,
https://www.facebook.com/pages/PKP-Sandwich/897335970282990 and
http://pkp2.altervista.org/. The project was registered at a public tender.
We have successfully completed and implemented most of the plans for the
project and the majority of reported activities (Table 7). During the im-
plementation period of the project, some of our originally planned activi-
ties were changed or abandoned. In the report, we would like to highlight
those deviations and which were most significant.

We wish to emphasize that there are almost no substantive deviations.
In the tender documents we provided, we will prepare bi-monthly briefings
on the status of the project. These activities were not carried out in such a